Ask which “megawatts” you’re looking at.
The figure from AEMO’s 2026 Electricity Statement of Opportunities that has stayed with me is 27%.
AEMO’s 2026 Electricity Statement of Opportunities estimates that operating data centres across the NEM had 2.2 GW of maximum connection capacity in the March quarter of 2026, and that actual demand that quarter came to about 27% of it in aggregate.
These are not proposals or sites still waiting on a substation. They are data centres that are already connected and running, and together they drew roughly a quarter of their connection capacity that quarter.
I think it gets far less attention than it deserves. Most of the debate about data-centre power in Australia is about getting capacity signed and energised, and much less is about what happens once it is.
Three numbers, one word
In practice, “capacity” is used for at least three different things.
Signed. What a network business has agreed to connect. Transgrid said on 26 August that about 1.5 GW of Western Sydney capacity had been allocated to signed data-centre connection agreements. New data-centre connections to the transmission network in the Sydney basin can only go ahead after user-paid network upgrades are delivered. Transgrid also said up to 2 GW more could be unlocked through network upgrades paid for by the data-centre proponents, including a new South Creek 500/330 kV substation and other substation and transmission line upgrades in Western Sydney.
A signed agreement doesn’t guarantee a connection, though. Network service providers advised AEMO of 225 data-centre projects at various stages of the NEM connection process in 2026. About 36% of the known projects on AEMO’s 2025 list have since been cancelled, at every stage of development. In AEMO’s own words, that includes “more than 30% of projects cancelled that were previously classified by NSPs as ‘committed’ (which typically means that a connection agreement is in place)”
Energised. What the grid can actually deliver, which depends on physical works being built. Kemps Creek is a recent case. Transgrid’s own environmental decision to proceed with a new 330 kV substation at Kemps Creek, a bulk supply point feeding Endeavour Energy’s network, was signed on 1 October 2026 That is Transgrid’s review under its own process, not a planning approval from another body, and the dates are not settled. Transgrid’s project page lists construction as proposed to start in June 2027 and end in December 2028, with commissioning in 2028 [4]. Its earlier fact sheet and community summary give a 2027–2029 construction period and 2029–2030 target commissioning, and its September
submissions report says the substation is proposed to be operational by 2029/2030. On any of those dates, that is more than two years from the October 2026 decision to the end of construction, and even then the supply has to move through the distribution network downstream.
So a single substation has more than one timeline across one organisation’s own documents. At Waymark we don’t choose between them. We record each date with its source and the date of the document, and note which document is the most recent.
Used. What is actually drawn, which is where the 27% comes in.
Most commentary stops at the gap between signed and energised. That gap is real and has been covered well, so this piece is about the third number.
Why used is so far below connected
Part of the gap is normal. AEMO calls current utilisation “relatively low” and estimates that a mature fleet will average 45–51% utilisation, depending on data centre type. Data centre operators often tell AEMO they expect utilisation to rise over five to 10 years as they ramp towards full capacity.
So even once the fleet matures, AEMO estimates only about half of connection capacity will be in use on average.
None of this is a criticism of operators. Connection capacity is sized with headroom and redundancy in mind, and sites take years to ramp up. It does mean, though, that connection capacity and load are different quantities, and the difference between them is large and lasting.
Where this shows up
Megawatt figures get repeated in deal announcements, forecasts, headlines and pitch decks. The number quoted is often a connection, signed or planned figure, and it is then read as if it were load.
If 2.2 GW of connected capacity carried about a quarter of that in actual demand in the March quarter, then a “2.2 GW market” and “2.2 GW of load on the grid” are not the same statement. And if signed capacity can be cancelled, and energised capacity runs well below its connection, then a headline MW figure can overstate real load in two separate ways.
For a lender, this affects revenue timing, because connected capacity that ramps slowly can mean demand, and some revenue, builds slowly too. For an infrastructure fund, it shapes what a site is worth now compared with what it might be worth later. For an equity analyst, it separates a capacity story from a demand story. And for anyone modelling the grid, used capacity is what the system actually has to carry.
The question I’d ask
When someone quotes a megawatt figure, my first question is whether it is signed, energised or used. My second is when it was true and where it came from.
AEMO, the AEMC and the network businesses publish a lot of the detail needed to answer that, and the rules are still changing. On 12 November 2026 the AEMC published its final rule on access standards. It defines a “large” inverter-based load, such as a data centre, as one with a nameplate rating of 30 MW or more, and applies the Schedule 5.3 access standards to those loads automatically, on transmission and distribution networks alike. The rule commenced on 12 November 2026, with a six-month grace period, to 12 May 2027, for connection applications that already had their technical requirements accepted and had not yet received an offer to connect. The difficulty is that this detail is spread
across long reports, project pages and decision statements, it takes careful reading to join up, and it dates quickly, so every finding needs an “as of” date.
That’s the work I do at Waymark Index. We publish written, source-cited research on whether Australian data-centre capacity is likely to be delivered. The Kemps Creek check above is typical of what we do on the projects we track, because knowing whether a project’s megawatts are signed, energised or used helps show when, and whether, they are likely to turn into revenue. Every figure we publish comes with its source.
All figures are from public sources listed below. All figures as of 13 November 2026
Sources
- Transgrid, “New transmission capacity in Sydney to be funded by data centres”, 26 August 2026.
https://www.transgrid.com.au/media-publications/news-articles/new-transmission-capacity-in-
sydney-to-be-funded-by-data-centres/ - AEMO, 2026 Electricity Statement of Opportunities (NEM), pp.36–37.
https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/nem_esoo/
2026/2026-electricity-statement-of-opportunities.pdf - Transgrid, Kemps Creek REF Decision Statement, October 2026 (signed 1 October 2026). This is
Transgrid’s own environmental determination as proponent and determining authority, not a
planning approval. https://www.transgrid.com.au/media/ioffqohb/kemps-creek-ref_decision-
statement_website-161026-1.pdf Also linked from [4]. - Transgrid, “Supply to Western Sydney Priority Growth Area” project page.
https://www.transgrid.com.au/projects-innovation/supply-to-western-sydney-priority-growth-area/ - AEMC, “Improving the NEM access standards – Package 2” (ERC0394), final determination and
final rule published 12 November 2026. https://www.aemc.gov.au/rule-changes/improving-nem-
access-standards-package-2 - Transgrid, Supply to Western Sydney Project Fact sheet, April 2026.
https://www.transgrid.com.au/media/frzfrr1c/supply-to-western-sydney-project-factsheet.pdf - Transgrid, Kemps Creek Substation REF Community Summary, June 2026.
https://www.transgrid.com.au/media/qoxdtgzb/kemps-creek-substation-review-of-environmental-
factors-community-summary-june-2026.pdf - Transgrid, Kemps Creek 330kV Substation Submissions Report, September 2026.
https://www.transgrid.com.au/media/ciojxt3q/supply-to-western-sydney-priority-growth-area-
kemps-creek-330kv-substation-submissions-report.pdf - AEMC, Information sheet, Improving the NEM access standards – Package 2, 12 November 2026.
https://www.aemc.gov.au/sites/default/files/2026-11/info_sheet_-_final_determination.pdf